National grid operator Transpower has advised that it will not be funding work to accelerate the Clutha-Upper Waitaki Lines Project (‘CUWLP’) transmission build in the lower South Island beyond the $10m committed by Contact and Meridian Energy in December 2019.
This means the CUWLP work programme is unlikely to be completed by the targeted commissioning date of June 2022, unless Contact and Meridian Energy contribute additional funding or the tenure of the Tiwai Point aluminium smelter is clarified.
Contact CEO Mike Fuge said the company’s commitment to helping accelerate the CUWLP work programme was unchanged, but Contact would not be making an additional financial contribution.
“We’ll continue to work with Transpower to see whether aspects of the CUWLP work programme can be optimised to mitigate delays from the recent COVID-19 restrictions. The goal is still to help move renewable electricity generation in the lower South Island north as soon as possible if the smelter closes or curtails its operations.”
About Contact Energy
Contact (contact.co.nz ) is one of New Zealand’s largest energy retailers and generators. We’re committed to a sustainable, low carbon energy future for New Zealand. We balance our commitment to lowering carbon emissions and producing renewable energy, with maintaining reliable access to energy for our customers. We generate electricity from hydro, geothermal and gas and have one of the most flexible generation portfolios in the country.
No comments yet
PaySauce Quarterly Market Update - Dec 2024
CHI - FY24 Results Date and Audio Conference Details
AIA - December 2024 Monthly traffic update
January 15th Morning Report
PF - Details of Interim Results Webcast
Scott Secures NZ$18 million in Global Contracts for Protein
January 14th Morning Report
AFT - NEW YEAR LETTER TO INVESTORS
TruScreen Invited to Present WHO AI Collaboration Meeting
January 13th Morning Report