Further investigation into Genesis’ Huntly Unit 5 combined cycle gas plant outage has indicated that return to service is now expected in late May 2024, as circuit breaker components are manufactured internationally.
High hydro storage, alternative plant availability and wholesale electricity market conditions have combined to mitigate the financial impact of the outage to date. Genesis is actively pursuing options to return the unit to service earlier and has material damage and business interruption insurance cover in place.
The financial impact of this event, based on current market conditions, plant and fuel availability, and mitigating factors is estimated to be in the range of $20 million to $30 million.
Updates on the return to service of the unit will be provided through the Transpower Planned Outage Coordination Process (POCP).
ENDS
No comments yet
PaySauce Quarterly Market Update - September 2024
October 2nd Morning Report
Rua Releases Annual Report for Year Ended 30 June 2024
SCL - Settlement of orchard sales
The Warehouse Group 2024 ASM and Director Nominations
AIR - Update on Chief Operational Integrity and Safety Officer
Comvita Limited - Annual Report 2024
September 27th Morning Report
Spark announces departure of Finance Director
FBU - Retail Entitlement Offer Opens